Ian Anderson, President and CEO of Trans Mountain, speaks during an event to mark the start of right-of-way construction for the Trans Mountain Expansion Project, in Acheson, Alta., Tuesday, Dec. 3, 2019. THE CANADIAN PRESS/Jason Franson

Trans Mountain pipeline will be the ‘best darn pipeline in the world,’ says CEO

Pipeline expansion is expected to take 30 to 36 months to build

The CEO of Trans Mountain says he’s “a little greyer” than he was 10 years ago when planning began for an expansion of the Edmonton-to-Burnaby oil pipeline but he’s still proud to oversee the official launch of Alberta construction.

Ian Anderson, who switched employers when the pipeline and its proposed expansion were sold to the federal government in 2018 for $4.5 billion, repeated a vow Tuesday to have expansion project pipe in the ground before Christmas.

Speaking in a frosty field west of Edmonton, he said the project has been steadily improved as it was repeatedly delayed over the years and is now set to be the “best darn pipeline in the world” with enhanced leak detection and thicker pipe in key segments.

He said the pipeline will take 30 to 36 months to build, which means it could be completed in the second half of 2022, but he declined to update the last cost estimate of $7.4 billion because the schedule is not yet confirmed.

Federal Minister of Natural Resources Seamus O’Regan said the event and the opening of the Canadian part of Enbridge Inc.’s Line 3 export pipeline last weekend make it a “good week” for Canada.

Alberta Energy Minister Sonya Savage said it’s “crucial” the Trans Mountain project not be subject to any further delays after it had to be approved twice by the federal government because of court challenges.

The expansion will nearly triple the 300,000-barrel-a-day capacity of the existing Trans Mountain pipeline, which carries crude oil and refined products from Edmonton to a terminal in Burnaby, B.C.

READ MORE: Trans Mountain received $320M in government subsidies in first half 2019: report

READ MORE: B.C. First Nations drop out of court challenge, sign deals with Trans Mountain

READ MORE: Feds won’t explain claim pipeline expansion will raise $500M in tax revenue

The Canadian Press


Like us on Facebook and follow us on Twitter.

Just Posted

More forest grants given

Community forest meant to benefit the community

Houston Legion auxiliary hosts annual hot turkey dinner

It was a hot turkey dinner with all the fixings on offer… Continue reading

Rescue truck purchase approved

Vehicle should be in-service by next summer

Local skaters showcase their talents

Special show on Dec. 13

‘Not a decision I came to lightly:’ Scheer to resign as Conservative leader

Decision comes after weeks of Conservative infighting following the October election

‘British Columbians are paying too much’: Eby directs ICBC to delay rate application

Attorney General David Eby calls for delay in order to see how two reforms play out

VIDEO: Octopus, bald eagle battle after bird ‘bites off more than it can chew’ in B.C. waters

B.C. crew films fight between the two feisty animals in Quatsino off north Vancouver Island

Couple who bought $120k banana duct-taped to wall say artwork will be ‘iconic’

Pair compared it to Warhol’s ‘Campbell’s Soup Cans,’ which was initially ‘met with mockery’

Race to replace Andrew Scheer could be a crowded one

Many familiar faces, such as Maxime Bernier, Jason Kenney, Doug Ford and Kevin O’Leary, have said no

Owner surrenders dogs chained up outside among scrap metal, garbage to BC SPCA

Shepherd-breed dogs were living in ‘deplorable conditions.’

B.C. plane crash victim identified; witnesses describe ‘explosion’

He was a flight instructor, charter pilot and owned an airstrip before leaving Alberta

Most Read