Site C dam project design has been changed to eliminate a separate bridge across the Peace River

Permits approved for Site C hydro dam

BC Hydro negotiating compensation with aboriginal communities, B.C. cabinet to decide soon whether $8 billion project will go ahead

VICTORIA – Both the federal and provincial governments have issued environmental assessment certificates for BC Hydro’s Site C dam, the proposed third hydroelectric project on the Peace River in northeastern B.C.

The approvals include dozens of legally binding conditions, including a $20 million farmland enhancement fund to offset river bottom land that would be flooded, and compensation for local aboriginal groups whose historic treaty rights to hunting, fishing and trapping would be affected.

Cost of the project, last estimated by BC Hydro at $7.9 billion, will factor into a final decision by the B.C. cabinet whether to go ahead with the dam. Energy Minister Bill Bennett has indicated he expects the final investment decision to be made by the end of 2014, and if it’s approved, work would begin immediately.

Among the 77 B.C. conditions is an aboriginal business participation strategy to share the estimated 10,000 person-years of construction work the dam project would generate.

Seven aboriginal communities affected by the proposal have been offered cash and Crown land to compensate for land lost by construction of the dam. All are signatories to Treaty 8, which ensures their rights to hunt, trap and fish as they did before the treaty was signed in 1899. Officials say five of the seven are currently in negotiations.

Situated near Fort St. John and downstream of the W.A.C. Bennett and Peace Canyon dams, Site C’s 1,050-metre-long earthfill dam would create a reservoir 83 km long and two to three times the current width of the river.

It requires two power lines built in the same corridor as the existing line, and six water turbine generators that would produce enough electricity to power about 450,000 homes.

BC Hydro estimates that because Site C would use water held back in the existing Williston Lake reservoir, it would generate 35 per cent of the energy as the Bennett dam with only five per cent of the reservoir area.

 

Just Posted

Greyhound cleared to end routes in northern B.C., Vancouver Island

Company says nine routes have dropped 30% in ridership in last five years

Houston athletes prepare for B.C. Winter Games

Eryn Czirfusz and U14 ringette team to represent Houston

BC BUDGET: New spaces a step to universal child care

Fees reduced for licensed daycare operators

BC BUDGET: NDP cracks down on speculators, hidden ownership

Foreign buyers’ tax extended to Fraser Valley, Okanagan, Vancouver Island

BC BUDGET: Payroll tax replaces medical premiums

Health spending to increase $1.5 billion for drugs, primary care teams

Therapy dogs make appearance at B.C. Games

The St. John’s Ambulance therapy dog program launches a pilot project at the 2018 Kamloops B.C. Winter Games

How to keep local news visible in your Facebook feed

Facebook has changed the news feed to emphasize personal connections. You might see less news.

Canucks fold 5-3 in first ever trip to Vegas

Daniel Sedin had two points as Canucks fall to the Golden Knights Friday night

That’s a wrap: B.C. Games results after Day 1

Vancouver-Coastal Zone 5 is in the lead for medals Friday at the Kamloops 2018 B.C. Winter Games

Sticking the landing at the B.C. Games

Gymnasts talk competition, B.C. Winter Games, and teamwork in Kamloops

$153M in federal cash to fund child care, education training in B.C.

Bilateral agreement will create 1,370 new infant and toddler spaces

A B.C. woman talks her life in the sex trade

A view into the life from one Kelowna prostitute and the issues it can cause for women

Twitter feed prays for — instead of preying on — B.C. MLAs

Non-partisan Christian group wants to support politicians through personalized prayer

Mills Memorial Hospital financing formula released

Regional taxpayers to pay $113.7 million for new facility.

Most Read