Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Coastal GasLink awards contract for camp near Burns Lake

Local residents to be consulted before location is picked

Houston prepares for projected growth

Transportation Master Plan anticipates traffic increase

Houston’s Pleasant Valley Plaza to host information session about bitcoin

Locals will have a chance to ask questions about the proposed farm

Northwest firefighters deployed to eastern Canada

They will help with fire suppression efforts in Ontario and Quebec

Work “well underway” for shared revenue in northwest B.C.

Resource Benefits Alliance developing proposal for the province

All-Indigenous teams break new ground, making BC Games history

This is the first time there have been dedicated Indigenous teams at the BC Summer Games

ZONE 7: Players’ insistence delivers North West softball team to BC Games

North West hasn’t had a girls softball team since 2010 but that changed at the Cowichan Summer Games

Recovery high schools could help teens before addiction takes hold: B.C. parents

Schools could provide mental health supports and let parents discuss their children’s drug use openly

Haida Gwaii village faces housing crisis, targets short-term rentals

Housing is tight and the village is pretty close to zero vacancy

Evacuation numbers remain at nearly 1,000 as B.C. wildfires rage on

200 firefighters and 18 helicopters were working to increase the containment of the fires

Man dead, woman in critical condition after stabbing in Quesnel

A 32-year-old man turned himself in to local RCMP Saturday, where he remains in custody

B.C. VIEWS: Unions regain control of public construction

B.C.’s 40-year battle swings back to international big labour

B.C. mining company, involved in 2014 spill, ordered to pay lost wages

Mount Polley Mining Company must pay wages to 26 employees who were laid off without proper notice

Two significant wildfires burning in southeastern B.C.

More than 20 fires were burning in the Southeast Fire Centre as of Saturday afternoon

Most Read