Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Bulkley Valley tourist industry adjusts to salmon closure

Businesses maintain philosophy of cooperation and enthusiasm as tourists begin arriving in Smithers.

Northwest family doctors win awards for B.C. launch of CHANGE Program

Northwest family doctors win awards for B.C. launch of CHANGE Program

Employer health tax may strain local governments

RDBN on the hook for an extra $24,000 by 2020

UPDATED: Horgan says B.C. defending its interests in Trans Mountain pipeline

Canadian finance minister’s update comes the same day Kinder Morgan shareholders plan to meet

Houston working around the clock to address flooding

River Forecast Centre upgrades advisory for Houston

VIDEO: Canadian Forces help flood-ravaged Grand Forks residents heal

Sgt. Bradley Lowes says the military is used to dealing with traumatic times

Chilliwack Chiefs make history with first RBC Cup win

In front of a huge and noisy crowd, the Chiefs claimed their first-ever national junior A title.

UPDATED: Majority of flood evacuees in Kootenay-Boundary allowed to return home

Officials hope to have all 3,000 people back in their homes by Monday night

B.C. Lions bring back 6-time all-star offensive lineman Jovan Olafioye

He was acquired by the Montreal Alouettes last year.

Whitecaps rally for 2-2 draw with FC Dallas

Vancouver climbed out of a two-nil hole to tie FC Dallas 2-2

B.C. VIEWS: Making sense of climate policy

Flood and fire predictions have poor track record so far

Chilliwack Chiefs moving on to RBC Cup final after thrilling win over Ottawa

Kaden Pickering scored the winning goal in the 3rd period as Chilliwack won their semi-final 3-2.

VIDEO: As floodwaters recede, crews assess the damage to Grand Forks’ downtown

More than four dozen firefighters and building inspectors came out to help

Wellington Dukes pull off epic upset of Wenatchee at RBC Cup

The Dukes are off to the championship game after downing the Wild 2-1 Saturday at Prospera Centre.

Most Read