Coastal GasLink pipe sections on the ground at the Port of Stewart during the week of Dec. 2, 2019. (Coastal GasLink photo)

Coastal GasLink receives first delivery of pipe sections

Company expects to begin welding and pipe laying in 2020

Coastal GasLink has pipe on the ground in northern B.C.

The natural gas pipeline operator confirmed Friday it has received its first shipments of pipe to storage sites north of Kitimat and in Chetwynd, and in Stewart.

Laying pipe is still months away.

“Steel pipe is one of the longest lead time items for any pipeline project and it is important that all materials are available for pipeline assembly and installation once site preparation is complete,” said its most recent project update.

Most of the pipe is being sourced in Canada, with the remainder coming from two mills in India and Japan.

Other delivery locations include rail siding sites at Chetwynd, Terrace, Prince George and Houston.

“Pipe will be delivered at varying times and locations over the next 18 months and is dependent on when the pipe arrives from the manufacturer, among other factors such as where it’s received, proximity to the storage site, and weather,” the email said.

Approximately 390 tonnes of pipe will go into the 670-kilometre route from the gas fields of northeast B.C. to the LNG Canada terminal in Kitimat.

As of Nov. 18, contractors have cleared 14 per cent of the route. Construction has employed 1,070 people.

So far, the majority of the clearing activity has concentrated on the two end sections (1 and 8), from Groundbirch to south of Chetwynd, and from south of Smithers to Kitimat with 41 per cent and 44 per cent completed, respectively.

Clearing has begun on sections 2 (south of Chetwynd to south of Mackenzie) and 3 (south of Mackenzie to north of Prince George).

Sections 4 through 7, from north of Prince George to south of Smithers, are still in pre-construction stages.

Another recent milestone was the opening of the first work camp. Sukunka Lodge, 42 kilometres south of Chetwynd, opened Oct. 30 and will house 700 workers when construction reaches its peak in the South Peace region next fall.

The assembly of LNG Canada’s work camp in Kitimat is also well underway.

READ MORE: LNG Kitimat work camp takes shape



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Province, feds, Wet’suwet’en announce progress in MOU talks

Community engagement process launched to implement northern B.C. First Nation’s rights and title

Province, feds, Wet’suwet’en announce progress in MOU talks

External community engagement process launched to help implement Wet’suwet’en rights and title

New design sought for community hall in Houston

The District of Houston is looking for a design for a new… Continue reading

Busy gym at leisure centre in Houston

There’s been a healthy response to the mid-June opening of the leisure… Continue reading

‘Don’t kill my mom’: Ryan Reynolds calls on young British Columbians to be COVID-smart

‘Deadpool’ celebrity responds to premier’s call for social influence support

Captain Horvat’s OT marker lifts Canucks to 4-3 win over Blues

Vancouver takes 2-0 lead in best-of-7 NHL playoff series with St. Louis

Widow of slain Red Deer doctor thanks community for support ahead of vigil

Fellow doctors, members of the public will gather for a physically-distanced vigil in central Alberta

Protesters showcase massive old yellow cedar as Port Renfrew area forest blockade continues

9.5-foot-wide yellow cedar measured by Ancient Forest Alliance campaigners in Fairy Creek watershed

Taking dog feces and a jackhammer to neighbourhood dispute costs B.C. man $16,000

‘Pellegrin’s actions were motivated by malice …a vindictive, pointless, dangerous and unlawful act’

Racist stickers at Keremeos pub leaves group uneasy and angry

The ‘OK’ hand gesture is a known hate-symbol

VIDEO: World responds to B.C. girl after pandemic cancels birthday party

Dozens of cards and numerous packages were delivered to six-year-old Charlie Manning

Expected fall peak of COVID-19 in Canada could overwhelm health systems: Tam

National modelling projections released Friday show an expected peak in cases this fall

Most Read